@Charlie

The Feds are still paying nothing for Phase II. Phase II doesn't meet Fed requirements for "cost/benefit" which are absurdly defined as cost per passenger mile. The $23M the State is paying for Phase II is bumped up by the $150M from the LaHood deal. Also, as part of that deal Fairfax's portion increases because they are building the Rt. 28 station & garage. Basically, all the other percentages remain the same.

The current total for Fairfax (including Rt 28) is $900-965M (of which 80% will be financed through special tax districts) and for Loudoun is $260M. The current total cost of Phase II is $2.7B (the slides, which are dated, show $2.5B)

http://www.connectionnewspapers.com/news/2012/apr/12/fairfax-county-board-opts-phase-2-dulles-rail/

by Falls Church on Apr 18, 2012 10:19 am • linkreport

Does this comment violate Greater Greater Washington's comment policy? If so, you can report it using this form and an editor will take a look.

What is the major reason you believe the comment violates the policy?
Comment is spam.
Comment attacks other individuals personally.
Comment criticizes the level of knowledge of another commenter or contributor.
Comment discourages others from posting their ideas.
Commenter is impersonating someone else.
Comment uses profanity or abusive language.
Comment advocates violent acts or harm to another.
Comment was posted in multiple areas of the site.
Comment is arguing about the comment policy.
Other:

Your name:
Your email:

Administrator pagespam