If you read the headlines in the Post and WAMU today, you might come away thinking that the DC government has decided not to try to build a streetcar line on Georgia Avenue or from Anacostia to Buzzard Point. But that would be wrong.

What’s going on?

What happened yesterday is the District Department of Transportation (DDOT) announced three finalists for its contract to design, build, operate, and maintain streetcar lines. Earlier this year, DDOT had planned for that contract to encompass all of the 22-mile streetcar system: an east-west line from Benning Road to Georgetown, a north-south line from Southwest to Takoma or Silver Spring, and a line from Anacostia to Southwest.

To make that possible, the mayor’s office had asked the DC Council to essentially set aside all of the money for the entire system right now.

While they insisted, vehemently, that they still support the streetcar system, the Council dedided they just weren’t ready to give it all of the money today. Therefore, this current bidding process can only legally encompass the lines which are in the six-year capital plan — the east-west line and the part of the Anacostia line from Bolling to the foot of the 11th Street Bridge.

The news stories have, accurately, reported that the current funding only lets the system grow to about 8.2 miles. Unfortunately, some of them also gave them impression that DC has “cut” the program. It’s going to happen slower, definitely, but that might not even be all bad.

It’s not really a surprise the council didn’t boost streetcar funding

Let’s say you want to start a company and are going to venture capital investors. You put together a rough business plan and they give you some seed money to hire some people. Then a few years go by, during which time your prototype gets delayed and you don’t talk to your customers. You then come back to investors asking for much more money, but your business plan still isn’t more detailed despite your promises to flesh it out. Would the investors fund you?

Even with crazy money in tech sometimes, it would be pretty tough. And it’s understandable that DC councilmembers balked at the mayor’s funding request. They continued authorizing about $600 million at a time when the starter line on H Street has been delayed and officials have given vague or no answers to questions. The mayor was asking for a very large amount of extra money, and politically, it just didn’t fly.

Since Terry Bellamy took over at the start of the Gray Administration and Carl Jackson came from Greenville, SC to run the transit programs, DDOT went mostly silent on the streetcar. There were a few required environmental study meetings, sure, but the agency basically stopped collaborating with groups like the Sierra Club or local BIDs, which it had done under Gabe Klein and Scott Kubly.

The mayor convened a task force chaired by City Administrator Allen Lew which included many business leaders. The business community was willing to talk about special taxing districts to help pay for the streetcar, but Lew ultimately decided not to even try a “value capture” system and instead just dedicated 25% of future new tax revenue to the streetcar.

At the same time, the government basically spent all of 2013 lying to the public about how the streetcar would open that year while everyone — at lower levels, anyway — knew it wouldn’t. Promises that DC would lay out detailed plans for things like where streetcar storage and maintenance yards would go went unfulfilled and questions about how it would work without overhead wires across the Mall and key viewsheds remain unanswered and unstudied (but studies are now beginning).

So, four years has gone by since the height of streetcar enthusiasm. In all that time, few detailed emerged, promises were repeatedly broken, and ties with allies atrophied.

The council said, give us a plan

Many councilmembers said, publicly and privately, that they still want to see the entire streetcar system built. The two leading mayoral candidates support the plan at least to a significant degree; both point to failures and mistakes along the way, which indeed happened.

But councilmembers, including Chairman Phil Mendelson, and also people in the budget office, say they just want more detailed plans. They want DDOT to do more legwork and answer more questions before they’ll hand over a blank check. I don’t entirely blame them.

Unfortunately, some in the Gray administration responded to the cuts by essentially saying, “okay, you didn’t give us the money, so that’s it for most of the lines.” That’s misleading. Councilmember Mary Cheh, who chairs the transportation committee, told the Post that the Gray team is being “childish” and not working with others. “You don’t take your marbles and go home,” Cheh said.

Sure, the cuts make things harder. Sometimes transportation projects can be a chicken-and-egg situation where you can’t know every single thing up front. The plans for the Metrorail system shifted between when construction started and when it ended (delaying the Green Line by years), for example. “Design-build” can be a more economical and faster way to get transportation projects built, but it also involves hiring your contractor before you have every detail laid out perfectly.

People who are more skeptical of the streetcar, like Phil Mendelson, are less tolerant of gaps in the plan which can get filled in during the design-build process; they don’t trust the team to fill the gaps well. Planning everything and then building it is slower and more expensive, and it becomes even more expensive when you go back and make changes along the way.

We can’t know every single detail now. DDOT and its contractor partners will learn from the mistakes of H Street as well as the (hopefully smaller) ones that come in the early stages of lines still scheduled to be built. The same thing happens with the road network, Metro, bike lanes, and any other large transportation facility.

Still, there also needs to be a role for the public in correcting the course along the way. Under Terry Bellamy, DDOT did not show a willingness to meaningfully involve others in streetcar discussions, which compounded mistakes. We do need to see how H Street works and then ask questions about how to do better on the next lines. We need to get answers, too.

Make it work now

The streetcar program will be good for DC. In some corridors, it will add capacity. It will drive higher transit ridership and connect communities. In some places, it will help kick-start economic development as well. It will have some bugs and then they will get worked out.

The most important thing is to build the full east-west line, and build it to its great potential. It’s already definitely going to have dedicated lanes on K Street, which will make it avoid the worst of the traffic. It also needs lanes, signal priority, and other features around Georgetown, Mount Vernon Square, and North Capitol Street to make it a speedy and attractive mode of travel. The streetcar needs to work well both operationally and for riders.

If it does, then public support for more lines will only grow, and the council will put money behind the rest of the lines. Already, Bellamy’s successor Matt Brown and Sam Zimbabwe, who is handling Jackson’s former duties, are steering the streetcar back toward the right track.

The lines are not “cut.” They’re just going to come later. It would have been a lot better if they could be built sooner, but with all of the mistakes during the Bellamy years, we lost that chance. It’s not the last chance, though.